This standard is applicable to hydrological calculations in all design stages and operation periods of small hydropower stations with an installed capacity of 50,000 kW and below, and can be used as a reference during the planning stage. Small hydropower stations with an installed capacity of less than 500kW can be appropriately simplified, see Appendix A.
SL 77-2013 Referenced Document
GB 50201 Standard for flood control*, 2014-06-23 Update
SL 252 Classification of water conservancy and hydropower projects and flood standards*, 2017-01-09 Update
SL 278 Regulation for hydrologic computation of water resources and hydropower projects(explanation)
SL 44 Regulation for calculating design flood of water resources and hydropower projects
SL 77-2013 history
2013SL 77-2013 Hydrological calculation code for small hydropower stations
1994SL 77-1994 Hydrological calculation norms for small hydro power