General Administration of Quality Supervision, Inspection and Quarantine of the People‘s Republic of China
Latest
GB 50825-2013
Scope
1.0.1 In order to improve the engineering quality of heating furnaces in iron and steel plants, unify the quality acceptance standards for heating furnaces in iron and steel plants, and ensure that the heating furnaces can achieve the required performance, this specification is formulated. 1.0.2 This specification is applicable to the heating furnace projects of newly built, rebuilt and expanded pusher type heating furnaces, walking beam type heating furnaces, walking bottom type heating furnaces, ring type heating furnaces, and trolley type heating furnaces in iron and steel plants . 1.0.3 In addition to implementing the provisions of this specification, the quality inspection of heating furnace projects in iron and steel plants should also comply with the relevant current national standards.
GB 50078 Code for construction and acceptance of chimney engineering
GB 50093 Code for construction and quality acceptance of automation instrumentation engineering*, 2013-01-28 Update
GB 50126 Code for construction of industrial equipment and pipeline insulation engineering
GB 50147 Code for construction and acceptance of high-voltage electric equipment installation engineering
GB 50149 Code for construction and acceptance of busbar installation of electric equipment installation engineering
GB 50150 Electric equipment installation engineering-standard for hand-over test of electric equipment*, 2016-04-15 Update
GB 50168 Construction and acceptance standards for cable lines in electrical installation engineering*, 2018-11-13 Update
GB 50169 English version of 10 engineering construction standards including "Code for Construction and Acceptance of Grounding Devices in Electrical Installation Engineering"*, 2020-01-10 Update
GB 50170 Construction and acceptance standards for rotating electrical machines in electrical installation engineering*, 2018-11-13 Update
GB 50171 Code for construction and acceptance of switchboard outfit complete cubicle and secondary circuit electric equipment installation engineering
GB 50204 Specification for construction quality acceptance of concrete structure engineering*, 2015-09-01 Update
GB 50205 Code for acceptance of construction quality of steel structures*, 2020-01-23 Update
GB 50211 Code for construction and acceptance of industrial furnace masonry*, 2015-08-01 Update
GB 50217 Design Standards for Power Engineering Cables*, 2018-02-12 Update
GB 50231 General code for construction and acceptance of mechanical equipment installation engineering
GB 50235 Code for construction of industrial metallic piping engineering
GB 50236 Code for construction of field equipment, industrial pipe welding engineering
GB 50255 Code for construction and acceptance of power conversion equipment electric equipment installation engineering*, 2014-01-29 Update
GB 50264 Code for design of industrial equipment and pipeline insulation engineering*, 2013-03-14 Update
GB 50275 Code for construction and acceptance of fan,compressor and pump installation
GB 50303 Code for acceptance of construction quality of building electrical engineering*, 2015-12-03 Update
GB 50386 Code for acceptance of engineering installation for mechanical equipment of rolling mill*, 2016-08-18 Update
GB 50387 Specifications for installation and acceptance of hydraulic, lubricating and pneumatic equipment engineering for metallurgical machinery*, 2024-04-20 Update
GBJ 87 Specifications for the design of noise control system in industrial enterprises
GB 50825-2013 history
2012GB 50825-2013 Code for quality acceptance of reheating furnaces in iron and steel works