This standard is applicable to the automation design of hydroelectric power stations for new or expanded or reconstructed projects with an installed capacity of 5 to 50MW and an outlet voltage level of 10kV or below. Hydropower stations with an installed capacity of less than 5MW can refer to the implementation, but their system configuration should be appropriately simplified to combine reliability, economy, and practicality.
SL 229-2011 Referenced Document
DL/T 5081 Specifications for design of automation of hydroelectric powerplants(explanation)
DL/T 5137 Technical code for designing of electrical measuring and energy metering device
SL 438 Specifications for design secondary circuit of hydroengineering
SL 229-2011 history
2011SL 229-2011 Automation design code for small hydropower station
2000SL 229-2000 Specification on atomation design of small hydropower station