The document establishes general principles for the execution of displacement piles which are installed in the ground without excavation or removal of material from the ground exept for limiting heave, vibration, removal of obstructions or to assist penetration. Piles are driven into the ground using impact, vibration, pressing, screwing or a combination of these methods. The material of displacement piles covered by this standard can be: steel, cast iron, concrete, timber, grout, combination of above.
DIN EN 12699:2001 history
2015DIN EN 12699:2015-07 Execution of special geotechnical works - Displacement piles; German version EN 12699:2015
2015DIN EN 12699:2015 Execution of special geotechnical works - Displacement piles; German version EN 12699:2015
2001DIN EN 12699:2001 Execution of special geotechnical work - Displacement piles; German version EN 12699:2000