This part stipulates the construction preparation, operating procedures and quality control, safety and environmental protection requirements and data collection during the preparation process of oil and water well bores. This section applies to the wellbore preparation and construction operations during downhole operations, including the process control of tubing running operations, sand exploration, sand flushing and well dredging, and casing cutting.
SY/T 5587.5-2004 history
2018SY/T 5587.5-2018 General well workover operation procedures Part 5: Wellbore preparation for underground operations
2004SY/T 5587.5-2004 Conventional Well Workover Procedures Part 5: Wellbore Preparation for Downhole Operations