NB/T 11319-2023
Hydropower Project Quality Management Procedures (English Version)

Standard No.
NB/T 11319-2023
Language
Chinese, Available in English version
Release Date
2023
Published By
Professional Standard - Energy  CN  /  NB
Latest
NB/T 11319-2023
 

Introduction

Core Value and Scope of Application of the Standard

NB/T 11319-2023, as an important industry standard in the field of hydropower engineering construction, has systematically constructed a quality management framework covering the entire life cycle for the first time. The standard is applicable to new, rebuilt and expanded hydropower engineering projects, emphasizing the four basic principles of excellent quality, safety and reliability, reasonable construction period and controllable cost.


Key points of quality management system innovation

Dimension Traditional model Requirements of this standard
Responsibility system Segmented division of responsibility Primary responsibility of construction unit + main responsibility of participating units
Control node Mainly in the construction stage Survey and design→equipment procurement→construction→commissioning entire process
Technical means Mainly in manual inspection Application of informatization + intelligent technology

Typical application cases

A large hydropower station project implemented clause 7.3.6 of this standard and implemented on-site supervision of the hydraulic generator set:

  • Established 12 key quality control points
  • Discovered and dealt with 3 types of material defects
  • The equipment acceptance rate reached 100%

Key link control requirements

Survey and design stage

Clause 5.4 clearly states that the design input must include 5 types of basic information:

  1. Laws, regulations and technical standards
  2. Surveying and mapping geological and hydrological data
  3. Equipment technical parameters
  4. Approval document requirements
  5. Similar project experience

Construction supervision stage

Clause 6.3.7 innovatively proposes the three-point control method:

  • Witness point (point W): witness of key processes
  • Stop-work inspection point (point H): mandatory acceptance node
  • Onsite station (point S): monitor key areas throughout the process

Suggestions for the implementation of the standard

Organizational guarantee measures

It is recommended that the construction unit establish a three-level quality management network in accordance with Clause 4.2.10:

Decision-making level Project Quality Committee
Management level Full-time quality management department
Execution level Quality team of participating units

Technical Implementation Path

In response to the construction machinery management requirements of Clause 8.4.9, it is recommended to adopt the QR code equipment management system:

  • One machine, one code identity authentication
  • Automatic reminder of maintenance cycle
  • Real-time monitoring of operating status

NB/T 11319-2023 history

Hydropower Project Quality Management Procedures

Topics on standards and specifications

Standard and Specification




Copyright ©2026 All Rights Reserved
Update: Tue, 28 Apr 2026 08:26:32 +0000