NB/T 11319-2023, as an important industry standard in the field of hydropower engineering construction, has systematically constructed a quality management framework covering the entire life cycle for the first time. The standard is applicable to new, rebuilt and expanded hydropower engineering projects, emphasizing the four basic principles of excellent quality, safety and reliability, reasonable construction period and controllable cost.
| Dimension | Traditional model | Requirements of this standard |
|---|---|---|
| Responsibility system | Segmented division of responsibility | Primary responsibility of construction unit + main responsibility of participating units |
| Control node | Mainly in the construction stage | Survey and design→equipment procurement→construction→commissioning entire process |
| Technical means | Mainly in manual inspection | Application of informatization + intelligent technology |
A large hydropower station project implemented clause 7.3.6 of this standard and implemented on-site supervision of the hydraulic generator set:
Clause 5.4 clearly states that the design input must include 5 types of basic information:
Clause 6.3.7 innovatively proposes the three-point control method:
It is recommended that the construction unit establish a three-level quality management network in accordance with Clause 4.2.10:
| Decision-making level | Project Quality Committee |
| Management level | Full-time quality management department |
| Execution level | Quality team of participating units |
In response to the construction machinery management requirements of Clause 8.4.9, it is recommended to adopt the QR code equipment management system: