This standard systematically regulates the full life cycle management requirements of piezometer devices for the first time, focusing on solving the standardization problem of seepage pressure monitoring in hydropower projects. The standard is applicable to seepage monitoring scenarios of concrete dams, earth-rock dams and other hydraulic structures and geotechnical engineering.
| Components | Material standards | Key indicators |
|---|---|---|
| Test pipe | GB/T 8162/GB/T 29038 | Pressure resistance ≥1.5MPa, pore diameter 0.5-1mm |
| Pipe mouth device | GB/T 197 | Thread accuracy 6g grade |
| Filter layer | DL/T 5178 | Graded gravel thickness ≥15cm |
Taking Tianshengqiao Hydropower Station as an example, attention should be paid to the installation of the piezometer at the dam foundation:
This standard integrates 7 current standards, including GB/T 29038 thin-walled stainless steel pipe technology and DL/T 5178 monitoring specifications, and makes special provisions for problems such as pipe corrosion and data distortion found in hydropower projects, which improves the accuracy by more than 30% compared with the old monitoring scheme.