Introduction

Core changes in the standard revision

Technical dimensions Requirements of the 2017 version New/revised content of the 2023 version
Voltage level Upper limit not specified The upper limit of the AC port voltage is determined to be 35kV
Functional requirements Basic power control 8 new functions such as primary frequency modulation and inertia response
Safety protection Basic insulation requirements 3 new requirements such as equipotential connection and capacitor residual energy protection

Analysis of key technical indicators

Core parameters of electrical performance

Energy storage converters must meet the following requirements under rated operating conditions:

  • Four-quadrant power dynamic adjustment range: active/reactive output is continuously adjustable within ±110% rated value
  • Conversion efficiency: Class A1 equipment charging and discharging efficiency ≥96% (including auxiliary power loss)
  • Fault ride-through capability: 0V voltage lasts for 150ms without disconnection from the grid

Comparison of typical application scenarios

Classification basis Class A1 (high voltage grid connection) Class B2 (low voltage power distribution)
Voltage level >1000V 380V
Dynamic reactive response ≤30ms Optional
Protection level IP54 (outdoor) IP20 (indoor)

Standard implementation recommendations

Product development focus

  1. Topology selection: Cascade topology is suitable for high voltage scenarios of 10kV and above
  2. Fault ride-through algorithm optimization: Need to support 3 consecutive low-high voltage ride-throughs
  3. Safety protection design: capacitor discharge time ≤ 5s (60V/20J)

Key points for testing and certification

  • Electromagnetic compatibility testing needs to distinguish between A1/B2 equipment limits
  • Type inspection includes 72-hour salt spray test (outdoor type)
  • Factory inspection requires 100% power frequency withstand voltage test

Technology evolution analysis

This standard introduces the inertia response requirement for the first time (formula: ΔP=-Tj/fn×df/dt×Pn), promoting the upgrade of energy storage systems from simple power regulation to grid support functions, where:

  • Inertia time constant Tj is set to 4-14 seconds
  • Response time ≤ 100ms, adjustment time ≤ 300ms

GB/T 34120-2023 history

  • 2023 GB/T 34120-2023 Technical requirements for power conversion system of electrochemical energy storage system
  • 2017 GB/T 34120-2017 Technical specification for power conversion system of electrochemical energy storage system
Technical requirements for power conversion system of electrochemical energy storage system

Topics on standards and specifications

Standard and Specification

GB 311.1-2012 Insulation co-ordination.Part 1:Definitions,principles and rules GB/T 29321-2012 Technical specification for reactive power compensation of PV power station GB/T 36548-2018 Test specification for electrochemical energy storage system connected to power grid GB 50150-2016 Electric equipment installation engineering-standard for hand-over test of electric equipment GB/T 36276-2023 Lithium-ion batteries for power energy storage NB/T 10563-2021 Technical Supervision Regulations for Relay Protection of Wind Farms DB61/T 1757-2023 Safety risk assessment specifications for electrochemical energy storage power stations GB/T 43526-2023 Technical regulations for connecting user-side electrochemical energy storage systems to distribution grids GB/T 34120-2017 Technical specification for power conversion system of electrochemical energy storage system GB/T 34133-2023 Energy storage converter testing technical regulations GB/T 36545-2023 Technical specifications for mobile electrochemical energy storage systems JBT13689-2019 Integrated low voltage reactive power compensation device GB/T 36547-2024 Technical regulations for the connection of electrochemical energy storage power stations to the power grid GB/T 42726-2023 Specification of supervision and control system for electrochemical energy storage station GB/T 36548-2024 Test procedures for connecting electrochemical energy storage power stations to the power grid GB/T 44026-2024 Technical specification for prefabricated cabin type lithium ion battery energy storage system GB/T 36558-2023 General technical requirements for electrochemical energy storage system of power system GB/T 43687-2024 Technical requirements for compressed air energy storage systems for electric power storage GB/T 44933-2024 Technical Specification for Flywheel Energy Storage Systems in Power Energy Storage



Copyright ©2025 All Rights Reserved